(8400-5040):5040,
=3360:5040,
=2:3,
甲提高工效后,甲乙的工作效率比为:
(3360+960):(5040-960)
=4320:4080,
=18:17;
设甲开始的工效为“2”,那么乙的工效为“3”,设甲在提高工效后还需a天完成任务,得:
(2×4+4a):(3×4+3a)=18:17,
解得a=
40 |
7 |
于是共有工程量为:
(2×4+4×
40 |
7 |
40 |
7 |
=(8+
160 |
7 |
120 |
7 |
=20+40,
=60;
所以原计划修好这条路的天数为:
60÷(2+3),
=60÷5,
=12(天).
答:两队原计划12天能修好这条路.